Click on each to view more information on our most recent projects.


CUSTOMER:
Muskoka Lakes Marina

GOAL:
An 80 x 60 steel building approximately 20 feet high was damaged in a fire and had to be demolished.

  • Separated scrap metal for recycling using a 20 tonne excavator.
  • Disposed of all fire damaged boats that were inside the structure.
  • Complete cleaning of site.
  • Concrete pad left in tact.
  • Removed all contaminated gravel around building and replaced with new gravel. 
  • Pressure washed concrete pad off on completion.

Time - 4 days

CUSTOMER:
Smith's Camp

GOAL:
 Clean up debris, damaged mobile homes and trailers after the F2 Tornado devastated the property.

  • Dismantled and removed all damaged trailers and mobile homes
  • Onsite within 10 hours to assist with the clean-up activities