CUSTOMER:
Muskoka Lakes Marina
Muskoka Lakes Marina
GOAL:
An 80 x 60 steel building approximately 20 feet high was damaged in a fire and had to be demolished.
- Separated scrap metal for recycling using a 20 tonne excavator.
- Disposed of all fire damaged boats that were inside the structure.
- Complete cleaning of site.
- Concrete pad left in tact.
- Removed all contaminated gravel around building and replaced with new gravel.
- Pressure washed concrete pad off on completion.
Time - 4 days
CUSTOMER:
Smith's Camp
Smith's Camp
GOAL:
Clean up debris, damaged mobile homes and trailers after the F2 Tornado devastated the property.
- Dismantled and removed all damaged trailers and mobile homes
- Onsite within 10 hours to assist with the clean-up activities